Update on CMAL’s Infrastructure works at Colintraive Ferry Terminal. 

George Leslie Limited completed dredging works between 12 and 15 October 2026. These works provide the under-keel clearance required for the new fully electric vessels. 

Enabling works for the new shore power infrastructure are planned to begin in November 2026. The programme includes a concrete plinth for the cable management system, a maintenance platform on the existing pier, foundations for a new low-voltage switch room and SSEN substation, and new underground chambers, ducts and cable supports. 

During these works, the ferry service will operate from the secondary slipway approximately 50 metres south of the terminal building. The current timetable is expected to continue, with only minor disruption around the port. 

ABB is expected to deliver the shore power electrical works in spring 2027. We will share further information about the construction programme and any changes affecting port users as the project progresses. 

Categories
News

CMAL Presentation on Harbour Revision Order

At the CC meeting on the 8th September CMAL offered the followiing presentation. The CC will be offering views on this consultation in due course. Let us know if you have questions or views on this to inform our response.

Categories
News

CalMac Survey closing soon

A survey on a proposed CalMac service reduction is open until midday on 24th May – share your views using the link below.

https://dunooncommunitycouncil.co.uk/community-surveys